SALEM WATER WORKS

 

Salem Water Works — Multiple Water Resources & Facilities

Lake Salinda Dam Improvements

The City of Salem owns and operates the Lake Salinda Dam and the 70-acre lake it impounds for water supply and recreation purposes. Lake Salinda is capable of producing one million gallons a day of drinking water, and is a critical component of the community as well as the surrounding Washington County area. Construction of the 40- foot earthen embankment and concrete spillway were originally completed in 1947.

The dam gradually deteriorated over the decades and was in desperate need of repair when a 20-foot portion of the concrete ogee-weir spillway failed on May 27, 2004 following several days of severe rainfall.

Given the magnitude and urgency of the project facing the City, The City of Salem quickly appointed Earth Tech, a distinguihed consulting, engineering and construction corporation that serves the water / wastewater, transportation, environmental, and facilities markets, to oversee and manage this major undertaking.

An overview summarizing the Lake Salinda Improvements follows.

ROLE OF EARTH TECH IN THE PROJECT

  • Dam Inspection
  • Hydrologic and hydraulic study
  • Design of dam improvements including a labyrinth spillway, embankment stabilization berm, and self-priming drawdown siphon

ROLE OF OTHER CONSULTANTS IN THE PROJECT

  • Aerial Photography: Lobo Aerial Surveys, Inc.
  • Geotechnical Engineer: ATC Associates
  • Construction Engineer: Saegesser Engineering
  • Contractor: Temple and Temple Excavating

BRIEF DESCRIPTION OF EARTH TECH'S CONTRIBUTION TO THE PROJECT

At the City’s request, Earth Tech visited the site the next day to assess the condition and provide recommendations for emergency stabilization of the spillway. Based on the recommendations, the City took immediate action to stabilize the failed portion of the spillway with a rock buttress and to lower the reservoir elevation with a temporary drawdown siphon. A local contractor began work on these recommendations within days.

Sustainable Design.

Previous inspections of the dam before the failure had noted several deficiencies in the embankment, intake tower, and spillway that were not directly related to the failure. After the emergency stabilization and drawdown were completed, Earth Tech and the City discussed the need for a long term solution as opposed to a repair that would target only the failure.

Earth Tech performed a hydrologic and hydraulic study as the first step, and designed dam embankment and spillway system improvements. The hydrologic and hydraulic study revealed that the existing spillway system had a peak discharge capacity of 8,400 cubic feet per second (cf/s) meaning it could only pass 43 percent of the Probable Maximum Precipitation (PMP) before overtopping of the dam embankment would occur.

IDNR requirements for high hazard dams, such as this dam, require dams to be capable of passing the full PMP before overtopping of the dam embankment occurs. To meet the full PMP design, the spillway system would have to be improved to pass a peak discharge of more than 30,000 cf/s, more than three times the existing discharge capacity. Because of this disparity, increasing the overall spillway system capacity was considered a key objective for permanent improvements to the dam.

Economic Considerations.

The hydrologic and hydraulic study determined that making all of the improvements necessary to bring the dam into full compliance with IDNR requirements would cost more than $1.7 million. The City could not afford the full cost in the short term. Postponing the improvements until the City could raise all of the funds was not an option due to the risk associated with leaving the spillway in its failed condition longer than necessary.

Earth Tech worked with the City and the IDNR to achieve a reasonable compromise between improving the condition of the dam and staying within the City’s budget constraints. It was agreed that the spillway capacity should at least be improved to pass 50 percent of the PMP in the short term with future improvements bringing the dam into full compliance for high hazard dams. Earth Tech split the improvements into two phases and prepared a bid package for the first phase that focused on replacing the failed spillway and providing additional spillway capacity. Earth Tech also included several smaller alternate items in the bid that the City could add or delete depending on the contractor’s cost and the City’s available funding.

Complexity

Site Conditions.

The geology and topography of the area around the dam as well as the condition of the dam itself created complexity in providing an economical solution that would address the failed spillway and the lack of spillway capacity. Site conditions precluded the construction of an auxiliary spillway (the most common approach for increasing spillway capacity) through either abutment.

The presence of rock at each abutment and steep topography made construction of an auxiliary spillway or widening of the existing spillway infeasible due to the cost of excavating such a large volume of rock. The complexity of the site conditions led Earth Tech to conclude that improved spillway capacity would have to be achieved without widening the existing spillway channel.

Constructability.

The ability to construct a replacement spillway was challenging because of the need to be able to control the lake level and divert flow around the structure for at least several weeks while the existing spillway was demolished and the replacement was constructed. The temporary siphon that was installed immediately after the spillway failure was only capable of lowering the lake one to two inches per day during dry weather. Due to nonfunctioning of the existing drawdown gates, the City and the IDNR expressed the need for a replacement drawdown mechanism that could be used in the future for both routine maintenance and emergency purposes. The objective was to address both constructability requirements and permanent drawdown needs.

Originality or Innovative Application of New or Existing Techniques

Innovative Spillway

Earth Tech’s design solution was to replace the ogee weir spillway with an innovative labyrinth weir spillway. The labyrinth weir increases the effective length of the spillway by creating a series of “W” shaped weirs in plan view. The existing 150-foot wide spillway channel was replaced with 780 feet of labyrinth weir length.

The result is a 35 percent increase in spillway peak discharge capacity compared to the original ogee weir. The dam is the first and only application of a labyrinth weir spillway in Indiana.

This spillway has greatly improved the safety of the dam by reducing the probability that the dam embankment will be overtopped. The new spillway system is able to pass 62 percent of the PMP before dam overtopping occurs. Future Phase 2 improvements will allow the spillway system to pass the full PMP design storm, but the labyrinth weir spillway was the first critical step in achieving full compliance. Drawdown System Utilizes Existing Intake Tower. A siphon designed and constructed through the existing water supply intake tower was used to control the lake level during spillway construction and for maintenance. The intake tower houses water supply pumps, which supply water to the onsite treatment plant, but are not capable of lowering the reservoir at an acceptable rate.

The siphon is capable of discharging flow at a rate of approximately 25 cf/s which translates to a reservoir drawdown rate of approximately one foot per day under dry flow conditions. The drawdown rate provided by the siphon was sufficient to allow the contractor to quickly lower the lake well below the elevation of the construction limits, thus providing sufficient flood storage capacity and time to reconstruct the spillway.

Future Value to the Engineering Profession and Perception by Public

Demonstration of New Technology.

This dam is by no means the only structure that could benefit from construction of a labyrinth weir spillway. Many other structures throughout the state and country face similar situations where the spillway capacity is undersized and yet it is not feasible to widen the spillway. The labyrinth design has paved the way for other consultants and dam owners to implement this new approach to provide an economical solution to increasing spillway capacity and creating safer dams.

Safety.

The Salinda spillway improvements have greatly reduced the potential that the dam could be overtopped during an extreme flood event. The integrity of the spillway structure has also been dramatically improved, minimizing the likelihood of a repeat spillway failure.

Additional safety improvement to the dam included the installation of a stabilization berm and toe drain along the downstream slope of the dam embankment to address the embankment’s insufficient factor of safety against sliding. The improvements to the dam and spillway provide tangible safety benefits as well as improving public perception of the dam’s safety.

Exceeding Client/Owner Needs

Earth Tech exceeded the needs of the City by responding quickly to an emergency situation, listening to the client’s needs, and providing an innovative solution to a complicated problem. Earth Tech was on site within hours of hearing from the City about the spillway failure. Earth Tech then continued this responsiveness by accelerating the planning, design, and permitting processes. Several meetings were held with the City’s key stakeholders to listen to their needs. Many smaller maintenance and safety items were incorporated into the design which resulted in a lower total cost than if the smaller items had been completed individually. Earth Tech exceeded the expectations of the City by providing a cutting edge solution for a difficult site condition. Lake Salinda Dam Improvements.

P HOTOGR A P H S - Click Image to View Larger Version
Downstream face of original ogee spillway Downstream face of ogee spillway after failure on May 27, 2004
Downstream face of ogee spillway after emergency repairs Spillway area after demolition of original ogee spillway
New labyrinth spillway during placement of rebar for spillway apron Downstream face of new labyrinth spillway
Upstream face of new labyrinth spillway Self-priming siphon pipe through existing lake intake tower
New stabilization berm on downstream slope of dam embankment  

# # #